A133 vs CMAR

CMAR is the project delivery method; A133 is an AIA agreement form often used when a construction manager provides preconstruction services and later performs construction with a GMP.

A133

  • Contract form selection
  • AIA document coordination
  • Owner-CM agreement drafting
Read the A133 definition

CMAR

  • Delivery method decisions
  • Preconstruction planning
  • Risk allocation strategy
Read the CMAR definition

Key differences

PointA133CMAR
TypeContract document.Delivery method.
FocusAgreement terms and responsibilities.How the project team is organized.
Common linkOften paired with GMP language.Often uses a GMP after preconstruction.

Example in context

An owner choosing CMAR may use A133 to contract with the construction manager and later amend the agreement when the GMP is established.