AFTERDRAFT

Construction Scheduling Terms

Scheduling terminology connects field progress, procurement, constraints, milestones, and contract completion dates.

Search intent

Use this page when reading schedule updates, lookahead plans, delay discussions, or milestone reports.

Common use cases

  • Updating schedules
  • Reviewing delays
  • Managing constraints
  • Planning field work

Terms in this collection

12 linked definitions.

Browse all terms
TermMeaning
Critical PathThe critical path is the sequence of activities that controls the earliest possible project completion date.
CPM Schedule

Critical Path Method Schedule

A CPM schedule is a schedule built with activity logic to identify the critical path and forecast project timing.
FloatFloat is the amount of time an activity can move without delaying a defined schedule milestone or project completion.
MilestoneA milestone is a key date or event used to track important points in the project schedule.
Lookahead ScheduleA lookahead schedule is a short-term schedule showing upcoming work over the next few weeks.
Pull PlanningPull planning is a collaborative scheduling method where teams plan backward from a milestone to define commitments and handoffs.
Constraint LogA constraint log tracks issues that must be resolved before planned work can proceed.
Procurement LogA procurement log tracks required materials, equipment, subcontracts, buyout status, lead times, and delivery dates.
Long-Lead ItemA long-lead item is a material or piece of equipment that requires a long time to purchase, fabricate, or deliver.
Master ScheduleA master schedule is the high-level schedule showing major phases, milestones, and overall project timing.
Milestone ScheduleA milestone schedule tracks major project dates and key completion points.
Extension of TimeAn extension of time adds contract time or schedule duration because of an approved delay or change.

Related collections