AFTERDRAFT

Construction Dictionary

Estimating & Procurement Terms

Learn estimating, bidding, procurement, buyout, allowance, and pricing terms used before and during construction.

Popular Terms

Browse All Terms

90 terms in estimating & procurement.

TermPlain-English definition
A
A151

Agreement Between Owner and Vendor

A151 is an AIA agreement form for owner-vendor relationships involving goods, equipment, or materials.
Additive AlternateAn additive alternate is optional work that can be added to the base bid if accepted by the owner.
AllowanceAn allowance is a budgeted amount included in the contract for work or materials not fully defined at the time of pricing.
AlternateAn alternate is a separately priced option that may be accepted or rejected by the owner.
B
BackchargeA backcharge is a cost charged to another party for work, damage, cleanup, delay, or correction they were responsible for.
Bid BondA bid bond is a surety bond that helps protect the owner if the selected bidder does not honor its bid.
Bid DocumentsBid documents are the drawings, specifications, forms, instructions, and contract requirements issued for pricing.
Bid PackageA bid package is a grouped set of scope, drawings, specifications, and instructions issued for pricing.
Biddability ReviewA biddability review checks whether bid documents are clear, complete, and organized enough for reliable pricing.
BPM

Building Product Manufacturer

A BPM is a company that makes products, materials, equipment, or systems used in buildings.
Budget CodeA budget code is a cost tracking code used to connect budgets, commitments, invoices, changes, and forecasts.
Budget EstimateA budget estimate is a cost estimate used to set or test the project budget.
BuyoutBuyout is the process of awarding subcontracts and purchase orders after pricing has been received and reviewed.
C
Cash AllowanceA cash allowance is a set amount of money included in the contract for work or materials not fully defined at award.
CommitmentA commitment is a subcontract or purchase order that commits project funds to a vendor, supplier, or subcontractor.
Committed CostCommitted cost is money already committed through contracts, purchase orders, or approved obligations.
Constraint LogA constraint log tracks issues that must be resolved before planned work can proceed.
ContingencyContingency is money or time reserved for unknowns, risks, or incomplete information.
Cost CodeA cost code is a tracking code used to organize project costs by scope, activity, or work category.
Cost TypeCost type classifies project costs by kind, such as labor, material, equipment, subcontract, or general conditions.
CPM Schedule

Critical Path Method Schedule

A CPM schedule is a schedule built with activity logic to identify the critical path and forecast project timing.
Critical PathThe critical path is the sequence of activities that controls the earliest possible project completion date.
D
Deductive AlternateA deductive alternate is optional work that can be removed from the base bid if accepted by the owner.
E
EscalationEscalation is an increase in labor, material, equipment, or subcontract cost over time.
EstimateAn estimate is a forecast of construction cost based on available information, assumptions, quantities, and pricing.
Estimated Cost to CompleteEstimated cost to complete is the forecasted remaining cost needed to finish the work.
Estimated Final CostEstimated final cost is the projected total cost at project completion.
Excusable EventAn excusable event is a delay or condition that may justify schedule relief under the contract.
Extension of TimeAn extension of time adds contract time or schedule duration because of an approved delay or change.
F
Fast TrackFast track is a project approach where construction starts before all design or procurement packages are complete.
FloatFloat is the amount of time an activity can move without delaying a defined schedule milestone or project completion.
Force AccountForce account is a method of tracking changed work based on actual labor, equipment, and material records.
G
G702

Application and Certificate for Payment

G702 is an AIA payment application form used to request and certify progress payment.
G703

Continuation Sheet

G703 is an AIA continuation sheet used with a payment application to show detailed line-item billing.
G705

List of Subcontractors

G705 is an AIA form used to identify subcontractors and portions of work.
G707A

Consent of Surety to Reduction in or Partial Release of Retainage

G707A is an AIA form used when a surety consents to reducing or partially releasing retainage.
G732

Application and Certificate for Payment, Construction Manager-Adviser Edition

G732 is an AIA payment application form used with construction manager as adviser project structures.
General Conditions CostsGeneral conditions costs are project costs needed to manage and support the work but not tied to one specific trade item.
I
Installed Production QuantitiesInstalled production quantities are measured amounts of work actually installed in the field.
Invitation to BidAn invitation to bid is a procurement notice inviting contractors or subcontractors to submit bids.
ITB

Invitation to Bid

An ITB is a formal invitation for contractors or suppliers to submit competitive bids.
J
Job CostingJob costing is the process of tracking actual and projected costs against a specific construction project.
L
Labor BurdenLabor burden is the additional cost of labor beyond base wages.
Lien WaiverA lien waiver is a document that waives or releases lien rights for payment received or expected.
Life Cycle CostLife cycle cost is the total cost of owning, operating, maintaining, and eventually replacing a building or system.
Long-Lead ItemA long-lead item is a material or piece of equipment that requires a long time to purchase, fabricate, or deliver.
Lookahead ScheduleA lookahead schedule is a short-term schedule showing upcoming work over the next few weeks.
Low BidderThe low bidder is the bidder that submits the lowest responsive price for the defined scope.
M
Master ScheduleA master schedule is the high-level schedule showing major phases, milestones, and overall project timing.
MilestoneA milestone is a key date or event used to track important points in the project schedule.
Milestone ScheduleA milestone schedule tracks major project dates and key completion points.
N
Notice of AwardA notice of award tells the selected bidder that the owner intends to award the contract.
O
Open BookOpen book means the contractor shares cost information, backup, and pricing details with the owner or project team.
OverbillingOverbilling happens when billed amounts exceed the value of work actually completed or earned.
P
Pay ApplicationA pay application is a contractor's request for payment for completed work and stored materials.
Phased ConstructionPhased construction breaks a project into separate stages or work packages.
Pre-Bid MeetingA pre-bid meeting is a meeting held before bids are due to explain project requirements and answer bidder questions.
Procurement LogA procurement log tracks required materials, equipment, subcontracts, buyout status, lead times, and delivery dates.
Procurement ScheduleA procurement schedule tracks purchasing, submittal, fabrication, and delivery timing for required materials and equipment.
Production QuantitiesProduction quantities are measured amounts of completed work used to track productivity and progress.
Production RateProduction rate is the amount of work completed per unit of time or labor.
Progress BillingProgress billing is billing for work completed during a defined period rather than waiting until the end of the project.
Progress PaymentA progress payment is a payment made for work completed or materials stored during the project.
Pull PlanningPull planning is a collaborative scheduling method where teams plan backward from a milestone to define commitments and handoffs.
Purchase OrderA purchase order is a contract document used to buy materials, equipment, or services.
Q
Quantity TakeoffA quantity takeoff is the process of measuring quantities of work or materials from drawings, models, or field information.
R
Request for ProposalA request for proposal is a procurement document asking firms to submit qualifications, approach, and pricing for a defined need.
Request for QuoteA request for quote asks a vendor, supplier, or subcontractor to price a defined item or scope.
RetainageRetainage is a portion of payment withheld until work reaches agreed completion milestones.
RFP

Request for Proposal

An RFP is a procurement document requesting proposals for a defined project, service, or scope of work.
RFQ

Request for Qualifications

An RFQ is a procurement document used to evaluate firms based on qualifications, experience, and capability.
Rolling ScheduleA rolling schedule is updated continuously as time moves forward and more project information becomes available.
Rough Order of MagnitudeA rough order of magnitude is an early, high-level cost estimate made with limited information.
S
Schedule of ValuesA schedule of values is a detailed allocation of the contract sum across work categories or line items.
Schedule UpdateA schedule update records current progress, revised dates, logic changes, and forecasted completion information.
Short Interval ScheduleA short interval schedule is a detailed near-term plan for upcoming work over a short period.
SOV

Schedule of Values

An SOV is a breakdown of the contract amount into line items used for billing and progress tracking.
Stored MaterialsStored materials are materials purchased for the project but not yet installed.
Subcontractor InvoiceA subcontractor invoice is a payment request submitted by a subcontractor for work performed or materials supplied.
Subcontractor Schedule of ValuesA subcontractor schedule of values breaks a subcontract amount into billing line items.
T
T&M

Time and Materials

T&M is a pricing method based on labor time, material costs, equipment, and agreed markups.
T&M Ticket

Time and Materials Ticket

A T&M ticket records labor, material, equipment, and sometimes subcontractor costs for time-and-materials work.
TimecardA timecard records labor time worked by a person or crew.
Two-Week LookaheadA two-week lookahead is a short-term schedule focused on work planned over the next two weeks.
U
UnderbillingUnderbilling happens when completed or earned work is not yet billed.
Unit PriceA unit price is a cost per measured unit of work, such as dollars per square foot, cubic yard, or linear foot.
V
VE

Value Engineering

VE is a process for evaluating alternatives that may reduce cost, improve constructability, or preserve value.
W
WBS

Work Breakdown Structure

A WBS breaks a project into smaller work packages, deliverables, or cost and schedule components.
WIP

Work in Progress

WIP refers to construction work that is underway but not yet complete.
Work Breakdown StructureA work breakdown structure organizes project scope into smaller components for planning, tracking, and control.

Related Categories