Search results for "Contract"

TermDefinition
Contract AdministrationContract administration is the process of managing contract requirements, communications, payments, changes, and closeout during construction.
Contract DocumentsContract documents are the written and graphic documents that define the parties' construction obligations.
Contract SumThe contract sum is the agreed amount payable for the work under the contract, as adjusted by approved changes.
Contract TimeContract time is the period allowed to achieve required completion milestones under the contract.
A101A101 is an AIA owner-contractor agreement form often used when the contract sum is a stipulated amount.
A102A102 is an AIA owner-contractor agreement form used when payment is based on the cost of the work plus a fee with a guaranteed maximum price.
A103A103 is an AIA owner-contractor agreement form used for cost of the work plus a fee without a guaranteed maximum price.
A104A104 is an abbreviated AIA owner-contractor agreement form for projects that need a shorter agreement structure.
A105A105 is a short AIA owner-contractor agreement form for smaller or less complex work.
A132A132 is an AIA owner-contractor agreement form used with a construction manager as adviser project structure.
A195A195 is an AIA agreement form associated with integrated project delivery.
A201A201 is an AIA general conditions document that defines many baseline rights, responsibilities, and procedures for construction contracts.
G705G705 is an AIA form used to identify subcontractors and portions of work.
G706G706 is an AIA closeout form used to support final payment by addressing payment of project debts and claims.
G706AG706A is an AIA closeout form used to support release of lien rights at final payment.
GCA GC is the contractor responsible for managing construction work and coordinating subcontractors.
OACAn OAC meeting is a regular project meeting between the owner, architect, and contractor.
A/EA/E refers to the design professional team responsible for architecture and engineering services.
A133A133 is an AIA agreement form used for certain owner and construction manager at risk arrangements.
A134A134 is an AIA owner-construction manager agreement form for certain CMAR projects using cost of the work plus a fee without a guaranteed maximum price.
A141A141 is an AIA agreement form for design-build projects where one design-builder contracts with the owner for both design and construction responsibilities.
A145A145 is an AIA design-build amendment form used to document commercial terms after design-build scope and pricing are developed.
A151A151 is an AIA agreement form for owner-vendor relationships involving goods, equipment, or materials.
Additional ServicesAdditional services are services beyond the baseline scope included in the agreement.
AIA Contract DocumentsAIA Contract Documents are standard contract forms and administrative documents commonly used in design and construction.
AllowanceAn allowance is a budgeted amount included in the contract for work or materials not fully defined at the time of pricing.
AORThe AOR is the licensed architect responsible for the architectural contract documents for a project.
ArbitrationArbitration is a private dispute resolution process where an arbitrator issues a binding or contract-defined decision.
As-Built DrawingsAs-built drawings document field conditions and changes from the original construction documents.
ASIAn ASI is a written instruction from the architect that clarifies or supplements the contract documents without changing contract cost or time.
B101B101 is an AIA agreement form for owner and architect services.
B102B102 is an AIA owner-architect agreement form used when the owner and architect define the architect's scope separately.
B103B103 is an AIA owner-architect agreement form intended for more complex projects.
B104B104 is an abbreviated AIA owner-architect agreement form.
B105B105 is a short AIA owner-architect agreement form for smaller or less complex projects.
B132B132 is an AIA owner-architect agreement form used with a construction manager as adviser project structure.
B133B133 is an AIA owner-architect agreement form used with certain construction manager as constructor or CMAR arrangements.
B143B143 is an AIA agreement form used between an architect and consultant.
BackchargeA backcharge is a cost charged to another party for work, damage, cleanup, delay, or correction they were responsible for.
Basic ServicesBasic services are the core architectural or professional services included in an agreement.
Bid DocumentsBid documents are the drawings, specifications, forms, instructions, and contract requirements issued for pricing.
BulletinA bulletin is a issued document that communicates proposed or required changes, clarifications, or additional information.
BuyoutBuyout is the process of awarding subcontracts and purchase orders after pricing has been received and reviewed.
C401C401 is an AIA agreement form used between an architect and consultant.
C402C402 is an AIA consultant agreement form for defined consulting services.
CACA is the process of administering construction-phase contract requirements, communications, reviews, and documentation.
Cash AllowanceA cash allowance is a set amount of money included in the contract for work or materials not fully defined at award.
CCDA CCD is a directive that authorizes changed work before the owner and contractor agree on final cost or schedule impact.
CECE is education completed to maintain knowledge, credentials, licenses, or professional development requirements.
Change DirectiveA change directive instructs the contractor to proceed with changed work before all commercial terms are finalized.
Change OrderA change order is a signed contract modification that changes scope, cost, time, or other contract terms.
ClaimA claim is a formal request or assertion seeking an adjustment, interpretation, payment, time, or other relief under the contract.
ClarificationA clarification explains existing requirements without necessarily changing contract scope, cost, or time.
CloseoutCloseout is the process of completing contract requirements and transferring final documentation at the end of construction.
CMARCMAR is a delivery method where a construction manager provides preconstruction services and then takes responsibility for delivering the project within an agreed price.
COA CO is a formal contract modification that changes scope, price, schedule, or other contract terms.
Code ComplianceCode compliance means the work meets applicable building, fire, accessibility, energy, zoning, or other code requirements.
COIA COI is a document that summarizes a party's insurance coverage for a project or contract.
CommitmentA commitment is a subcontract or purchase order that commits project funds to a vendor, supplier, or subcontractor.
Commitment Change OrderA commitment change order modifies a subcontract or purchase order.
Committed CostCommitted cost is money already committed through contracts, purchase orders, or approved obligations.
Construction Manager as AdviserConstruction manager as adviser is a delivery structure where the construction manager advises the owner but does not hold the prime construction contract.
Construction Manager at RiskConstruction Manager at Risk is a delivery method where the construction manager advises during preconstruction and later assumes construction cost and delivery risk.
ContingencyContingency is money or time reserved for unknowns, risks, or incomplete information.
CORA COR is a contractor request asking for approval of a change in cost, time, or scope.
Correction of WorkCorrection of work is the obligation to fix work that does not meet contract requirements.
Cost Plus ContractA cost plus contract reimburses allowable project costs plus an agreed fee or markup.
Cost TypeCost type classifies project costs by kind, such as labor, material, equipment, subcontract, or general conditions.
CSI DivisionA CSI division is a numbered category used in MasterFormat to group related specification sections and work results.
DefaultDefault is a failure to meet a contractual obligation.
DeficiencyA deficiency is work that does not meet contract requirements, quality standards, code, or approved submittals.
Delivery MethodDelivery method is the contract and team structure used to design, procure, and build a project.
Design-Bid-BuildDesign-Bid-Build is a delivery method where design is completed before the project is competitively bid and built.
Design-BuildDesign-Build is a delivery method where one entity is responsible for both design and construction services.
Design-BuilderA design-builder is the entity responsible to the owner for both design and construction under a design-build agreement.
DisputeA dispute is a disagreement between project parties about contract requirements, payment, time, quality, scope, or responsibility.
Division 00Division 00 contains procurement and contracting requirements in the project manual.
EasementAn easement is a legal right to use part of a property for a specific purpose.
EscalationEscalation is an increase in labor, material, equipment, or subcontract cost over time.
Excusable EventAn excusable event is a delay or condition that may justify schedule relief under the contract.
Extension of TimeAn extension of time adds contract time or schedule duration because of an approved delay or change.
Field OrderA field order is a written direction issued in the field to address work or coordination needs.
Final CompletionFinal completion is the point when all contract work, closeout documents, and remaining obligations are complete.
Final PaymentFinal payment is the last payment made after required work, closeout documentation, releases, and contract conditions are satisfied.
Finish ScheduleA finish schedule is a drawing or table that identifies finish materials by room, surface, or location.
G701G701 is an AIA form used to document an approved change order.
G702G702 is an AIA payment application form used to request and certify progress payment.
G703G703 is an AIA continuation sheet used with a payment application to show detailed line-item billing.
G707AG707A is an AIA form used when a surety consents to reducing or partially releasing retainage.
G710G710 is an AIA form used for architect instructions that clarify or supplement the contract documents without changing cost or time.
G715G715 is an AIA form used as a supplemental attachment related to insurance certificate information.
G731G731 is an AIA change order form used with construction manager as adviser project structures.
General ConditionsGeneral conditions are contract provisions that define baseline rights, responsibilities, procedures, and relationships for the project.
GMPA GMP is a contract amount that sets the maximum price an owner should pay for the defined construction scope, subject to approved changes.
Guaranteed Maximum PriceGuaranteed Maximum Price is a contract pricing structure that caps the owner's payment for defined work, subject to approved changes.
Information RequirementAn information requirement describes the data an owner, designer, contractor, or operator needs for a defined purpose.
Initial Decision MakerAn initial decision maker is the party or person designated to make an initial decision on certain claims or disputes.
Instruments of ServiceInstruments of service are documents, drawings, models, specifications, and other work products prepared by design professionals for a project.
Invitation to BidAn invitation to bid is a procurement notice inviting contractors or subcontractors to submit bids.
IPDIPD is a collaborative delivery approach that aligns owner, designer, and builder incentives around shared project outcomes.
ITBAn ITB is a formal invitation for contractors or suppliers to submit competitive bids.
Liquidated DamagesLiquidated damages are a contractually stated amount owed for certain delays or failures to meet agreed requirements.
Means and MethodsMeans and methods are the contractor's chosen techniques, sequences, procedures, and resources for performing the work.
Mechanic's LienA mechanic's lien is a legal claim against property for unpaid labor, materials, or construction services.
MediationMediation is a dispute resolution process where a neutral mediator helps parties try to reach a voluntary settlement.
Milestone ScheduleA milestone schedule tracks major project dates and key completion points.
ModificationA modification is a written change to the contract documents after the contract is executed.
Notice of AwardA notice of award tells the selected bidder that the owner intends to award the contract.
Notice to CureA notice to cure is a formal notice requiring a party to fix a default, deficiency, or failure to perform.
NTPAn NTP is a formal notice authorizing a contractor to begin work or start a defined contract activity.
Open BookOpen book means the contractor shares cost information, backup, and pricing details with the owner or project team.
OverbillingOverbilling happens when billed amounts exceed the value of work actually completed or earned.
Owner Change OrderAn owner change order modifies the prime contract between the owner and contractor.
Owner-Architect AgreementAn owner-architect agreement is the contract between the owner and architect for professional design and administration services.
Owner-Contractor AgreementAn owner-contractor agreement is the prime contract between the owner and the contractor for construction work.
Owner's RepresentativeAn owner's representative is a person or firm that helps the owner manage project decisions, communication, risk, and performance.
Pay ApplicationA pay application is a contractor's request for payment for completed work and stored materials.
Payment BondA payment bond is a surety bond that helps protect subcontractors and suppliers if they are not paid.
Performance BondA performance bond is a surety bond that helps protect the owner if the contractor fails to perform the work.
PMPM is the management of project scope, cost, schedule, communication, risk, procurement, and delivery.
PreconstructionPreconstruction is the planning phase before construction begins, when teams refine scope, budget, schedule, logistics, and procurement strategy.
Prime ContractA prime contract is the main contract between the owner and the contractor or construction manager.
Procurement LogA procurement log tracks required materials, equipment, subcontracts, buyout status, lead times, and delivery dates.
Progress PaymentA progress payment is a payment made for work completed or materials stored during the project.
Project EngineerA project engineer supports construction management tasks such as RFIs, submittals, drawings, meeting minutes, and document control.
Project ManagerA project manager is responsible for managing project scope, cost, schedule, contracts, communication, and risk.
Project ManualA project manual is a bound or digital set of procurement requirements, contract requirements, and technical specifications.
Purchase OrderA purchase order is a contract document used to buy materials, equipment, or services.
Quantity TakeoffA quantity takeoff is the process of measuring quantities of work or materials from drawings, models, or field information.
Rejected WorkRejected work is work that is not accepted because it does not conform to the contract documents.
Request for ClarificationA request for clarification asks the design team or owner to clarify unclear information before work proceeds.
Request for QuoteA request for quote asks a vendor, supplier, or subcontractor to price a defined item or scope.
RetainageRetainage is a portion of payment withheld until work reaches agreed completion milestones.
RFIAn RFI is a formal request used to clarify drawings, specifications, contract documents, or project requirements during construction.
Schedule of ValuesA schedule of values is a detailed allocation of the contract sum across work categories or line items.
Scope of WorkA scope of work describes the work a party is responsible to perform.
Self-Performing ContractorA self-performing contractor performs work with its own crews instead of subcontracting all of it out.
Shop DrawingA shop drawing is a contractor- or fabricator-prepared drawing showing how specific work will be fabricated, assembled, or installed.
Single-Point ResponsibilitySingle-point responsibility means one contracting entity is responsible for both design and construction obligations.
Site InstructionA site instruction is a written direction about work or site activity issued during construction.
SOVAn SOV is a breakdown of the contract amount into line items used for billing and progress tracking.
SpecificationsSpecifications are written requirements that describe materials, products, workmanship, performance, and administrative procedures.
Standard Test MethodA standard test method is a published procedure for performing a test in a consistent and repeatable way.
Stipulated SumA stipulated sum is a fixed contract price for a defined scope of work.
Stored MaterialsStored materials are materials purchased for the project but not yet installed.
SubcontractorA subcontractor is a company hired by a contractor to perform a specific portion of the construction work.
Subcontractor InvoiceA subcontractor invoice is a payment request submitted by a subcontractor for work performed or materials supplied.
Subcontractor Schedule of ValuesA subcontractor schedule of values breaks a subcontract amount into billing line items.
SubmittalA submittal is information submitted by a contractor for review, such as product data, samples, shop drawings, or schedules.
Submittal WorkflowA submittal workflow defines the review path a submittal follows before it is closed.
SubmitterA submitter is the person or company responsible for sending a submittal for review.
Substantial CompletionSubstantial completion is the point when the project is sufficiently complete for the owner to use it for its intended purpose.
Supplementary ConditionsSupplementary conditions modify or add to the general conditions for a specific project.
SuretyA surety is a company that backs a bond and may be responsible if the bonded contractor fails to meet obligations.
T&M TicketA T&M ticket records labor, material, equipment, and sometimes subcontractor costs for time-and-materials work.
Termination for CauseTermination for cause ends a contract because a party failed to meet material obligations.
Termination for ConvenienceTermination for convenience allows a party, often the owner, to end a contract without contractor default.
The WorkThe work means the construction and services required by the contract documents.
Trade ContractorA trade contractor performs a specific construction trade or specialty scope.
UnderbillingUnderbilling happens when completed or earned work is not yet billed.
WarrantyA warranty is a promise or obligation related to the quality, performance, repair, or replacement of work or products.
WIPWIP refers to construction work that is underway but not yet complete.
Witness StatementA witness statement is a written account from someone who observed an event, condition, incident, or dispute.